Key Points for Heat Meter Installation and Commissioning

For a heat meter to work accurately and efficiently, its suitability for the installation and its characteristics must be carefully examined — such as the PN pressure class and the maximum fluid temperature. Pressure loss must also be considered in circulation pump calculations.

Points to consider when installing a heat meter

Suitability and characteristics of the heat meter

For a heat meter to work accurately and efficiently, its suitability for the installation and its characteristics must be carefully examined. This means taking into account characteristics such as the PN pressure class and the maximum fluid temperature. Pressure loss must also be considered when calculating the circulation pump.

Installation and connection

If the diameter of the pipeline is smaller than the meter, a suitable reducer must be used. It is important to fit a strainer of pipe diameter upstream of the heat meter in the direction of flow. This keeps the water passing through the meter clean and contributes to a long service life.

Cleanliness of the system

Clean system water is essential for the heat meter to work properly. A sediment trap on the return line in the boiler room is therefore recommended.

Shut-off valves and ease of service

Shut-off valves of pipe diameter must be installed so that the heat meter–strainer group and the sensor pocket can be serviced. In addition, the plastic blind plug supplied with the meter must be fitted to the lower body during the first installation.

System checks and cleaning

At the end of construction, the calculator units of the heat meters should be installed after the system tests and leak checks have been carried out. It is also important to clean the strainers and repeat this cleaning periodically.

Installation and accessibility

For accurate measurement, a straight pipe section of 10×DN upstream and 8×DN downstream of the meter should be left. The heat meter and strainer must also be easily accessible at the installation location.

Installation safety and protection

Water leaks, seepage and drips in places such as service shafts, plant rooms or service galleries where the heat meter is installed must be eliminated beforehand. Heat meters must also be protected from environmental shocks, vibration and the risk of damage.

Hydraulic conditions and chemicals

Care must be taken that unsuitable hydraulic conditions (cavitation, water hammer) do not damage the heat meter. Make sure the sensor cables are not damaged during installation. Obtain a guarantee from the supplier that any chemicals used in the heating system will not harm the installation or the heat meter.